Completed Project Summary for JMS Energy
Project Title: Wake Wind Location: Floydada, TX Year: 2023
Project Overview: In 2023, JMS Energy successfully completed the Wake Wind project in Floydada, TX. This comprehensive project involved multiple complex tasks aimed at enhancing and upgrading the energy infrastructure. Below is a detailed breakdown of the key tasks completed during this project:
PMT Decommissioning (PMT Decom): JMS Energy began with the decommissioning of existing Power Management Transformers (PMT). This step was crucial for clearing the way for new installations and ensuring the overall safety and efficiency of the project.
Cabling to Data Termination Assembly (All Cabling to DTA): The team meticulously managed the installation of all cabling to the Data Termination Assembly (DTA). This involved ensuring proper routing, secure connections, and compliance with industry standards to facilitate seamless data transmission.
PMT Repairs: During the project, necessary repairs to existing PMTs were conducted to extend their operational life and improve performance. This involved diagnosing issues, replacing faulty components, and conducting thorough testing.
Cable Repairs and New Cable Installation (Cable Repairs, New Cables to DTA): JMS Energy addressed existing cable issues by performing extensive repairs and installing new cables to the DTA. This process ensured a robust and reliable connection between various components of the energy infrastructure.
New Vault Installation (New Vault): A new vault was installed to house essential equipment and protect it from environmental factors. This included excavation, construction, and securing the vault to meet project specifications.
New Tower Wiring: The team carried out the installation of new wiring for towers, ensuring they met the required standards for safety and functionality. This included running cables, securing connections, and testing the wiring systems.
Bus Bar Configuration (Assume Bus Bar Configuration): JMS Energy assumed responsibility for configuring the bus bar, a critical component for distributing electrical power within the system. Proper configuration ensured efficient power management and minimized potential issues.
Preparation before Erection (Prep before Erection): Extensive preparation work was conducted before erecting new structures. This included site clearing, foundation work, and setting up necessary equipment to facilitate smooth and safe erection processes.
Electrical Completion: The project involved comprehensive electrical work, from initial installations to final connections. This included testing and commissioning all electrical systems to ensure they operated as intended.
Fiber Optic Terms and OTDR Testing: JMS Energy handled the termination of fiber optic cables, a vital task for maintaining high-speed data transmission. Additionally, Optical Time Domain Reflectometer (OTDR) testing was conducted to verify the integrity and performance of the fiber optic links.
The Wake Wind project in Floydada, TX, was a testament to JMS Energy’s expertise in managing complex energy infrastructure projects. Through meticulous planning, execution, and testing, the team delivered a robust and reliable system that met all project specifications and industry standards.